Windows and blockwork arrive and are installation begins. Any window or door that
needs to be in place before the blockwork can be done are installed. The 3 largest upstairs windows need a lifter to get to their final position and the other
upstairs windows can wait.
Given the weight of double glazed windows some of the glass will be
installed on-site. The carpenters are installing the windows and do some final
stud framing before the brickwork starts.
The brickies spend most of the first day ensuring that the bricks will
be laid up correctly with cuts kept to a minimum with the required expansion
joints.
By the second day, we're getting some height and we have the discussion around the bagging of the finished blocks.
It’s also time to make selections for much of the kitchen appliances
prior to the kitchen being built to ensure dimensions are correct.