All of the roof is on barring the bit where the carport will cut into
the main roof. The iron cladding is up and the Alucoil fixers have fitted the top
hats and measured for the panels.
Kev is king of the castle and master of the flashing but it won’t be completed until the Alucoil is on as much of the top capping covers both materials.
The carpenters do a bit more such as the stud wall in the cellar so the
electrician can get the switch plates in place.
The rain damaged ceilings in 17 are repaired and replaced as is the ceiling in the hall of 19 so the electrician can drill the holes for the lights and place the wires for the ceiling fans.
The bin has gone and room is being made so the carport construction can start and the plumber can get the gas and water connected.
Steel posts are purchased to house the meter boxes and the plumber agrees on the path for the sewer and to help get things moving, Paul spends quite a few hours digging the trench about 3 meters to meet up with the new street connection.