Week Three - cellar floor is cemented

More plumbing is done, more so for 17 and the bathroom is pretty well set to go.
Henry, the stone mason joins the weekly site meeting again and it's agreed to have a cement plinth across the bottom of the front wall over the waterproofing.

The reo came and went on Monday to return Tuesday on a smaller truck.
The cellar is framed and the floor is poured early on Friday.
It's comforting to know that the new hole, soon to be a cellar is very dry, nothing sneaking in.

With final internal dimensions of 2900 x 5800 and a depth of 2400, after stairs are put in, there should be enough room for a bottle or 2 amongst the stuff you'd normally find in a shed.

Time spent off site selecting window frame colours, finalise the air conditioning specs and solar options prior to commencing the electrical fit-out.